Broadway Bridge Replacement Project
 
Detour Broadway and EverettBroadway and HewittBroadway BridgeHewitt and Cedar
Click on a camera icon to view the current camera image.


Project Description:

The Broadway Bridge is more than 100 years old and in need of replacement. We will demolish and replace a 100-feet span by 100-feet wide bridge over the Burlington Northern Santa Fe (BNSF) railroad main line. The bridge span is located on Broadway between Hewitt Avenue and California Street.

 

Current weight restrictions:

Effective June 19, 2014, the City Engineer has extended a weight-limit restriction to all lanes of Broadway between Hewitt Avenue and California Street. Vehicles weighing more than 11 tons must use alternate routes.  The weight restrictions shall remain in effect across all lanes until the bridge is permanently closed for demolition.

 

Timeline:

Contract Awarded to Interwest Construction, Inc.  October 2014

Begin Detour Route construction: December 2014

Begin Bridge Demolition:  January 2015

Complete Construction: Early 2016

 

Why will it take so long?
No over-track work allowed while trains are running – 44 freight trains on average per day.

No over-track work allowed from October to December – BNSF major freight season restriction.

Total demolition and new construction of the bridge with new foundation and abutments (as opposed to swapping out a bridge span like the temporary Skagit River bridge.)

Different vertical alignment – for improved sight distance and railroad clearance.


Project Manager:

Ryan L. Sass, PE

City Engineer

Email: everetteps@everettwa.gov

Phone: 425-257-8800

<< < Previous Next > >>
 

Design & Construction Management
Ryan L. Sass, P.E., City Engineer

3200 Cedar St.
Everett, WA 98201
T: 425-257-8800
F: 425-257-8856
E:
calendar Getting to Everett SiteMap Legal Stuff Community Movies Experience Everett  
Back to main site